ACCA PM Relevant Costing Notes: Short-Term Decisions [Worked Examples]

ACCA PM relevant costing notes: make-or-buy, special order, shutdown and further processing, worked examples

ACCA PM relevant costing decides which costs matter in a short-term decision and which costs to ignore. Only future, incremental cash flows count. This note explains the rule, materials, labor and overheads, and the make-or-buy, special order, shutdown and further processing decisions in areas C1 and C5.

PM is a three hour, 100 mark exam: Section A 30 marks, Section B 30 marks, Section C 40 marks, and the pass mark is 50 percent. One Section C question comes from decision-making or budgeting. PM passed 42 percent of candidates in September 2026, the lowest of the five Applied Skills papers. According to the ACCA timetable, PM sits on Wednesday 9 December 2026.

Open the ACCA notes hub.

ACCA PM relevant costing: the rule in one paragraph

ACCA PM relevant costing asks one question: what future cash flow changes because of this decision? Only future, incremental, cash costs and revenues count. Sunk costs, committed costs, depreciation and absorbed fixed overheads stay out. Opportunity cost counts too, because using a scarce resource elsewhere has a price.

The test is simple. For every cost, ask whether cash leaves because of this decision. If the answer is no, the cost is irrelevant, however large it looks. A cost already spent never counts. Treat a cost payable under any option as committed. A cost that only moves between cost centres is an apportionment, not a cash flow. Give a short reason for each item, because the examiner awards marks for it.

What counts as relevant, and what does not

Four types of cost are relevant: future cash costs caused by the decision, incremental revenues, opportunity costs, and avoidable fixed costs. Four types are not: sunk costs, committed costs, depreciation and other non-cash items, and absorbed fixed overheads that do not change in total.

Cost or itemRelevant?Reason
Future incremental cash costYesCash flow caused by the decision
Opportunity costYesBenefit given up elsewhere
Avoidable fixed costYesCost saved if the decision changes
Sunk costNoMoney already spent
Committed costNoPayable under every option
Depreciation and book valuesNoNon-cash items
Absorbed fixed overheadNoApportionment only

Materials: replacement cost, resale value or nothing

Materials follow three rules. When the business must buy the material, the relevant cost is the current purchase price, not the price in the stock records. If the material sits in stock for regular use, the relevant cost is the current replacement cost, because using it here means buying more. If the material is in stock with no other use, the relevant cost is its resale value. Historic cost never matters.

Labor: spare capacity changes everything

Labor depends on capacity. When staff have spare time and keep their pay anyway, the relevant labor cost is zero. If the business must hire staff or pay overtime, the extra pay is relevant. If staff work at full capacity and must move from other work, the relevant cost is the wages plus the contribution lost elsewhere, after deducting the labor cost itself. A supervisor the business hires for the order counts as relevant, while one already on the payroll does not.

Overheads, depreciation and other non-cash items

Include only overheads that change because of the decision. Ignore absorbed fixed overheads, because the total does not change. Depreciation is never relevant, because it is a book entry with no cash effect. If the decision requires buying a new machine, the purchase price is a relevant cash outflow, and any resale value at the end is a relevant cash inflow.

ACCA PM relevant costing worked example 1: make or buy

Northgate Co needs 2,000 units of component K each month. It can make the component in house or buy it at $40 per unit from a supplier. The make cost per unit is materials $18, labor $12, variable overhead $6 and absorbed fixed overhead $9. In addition, each unit takes 3 machine hours. If Northgate buys, the business can use the freed hours on product Z, which earns $5 contribution per machine hour. A $3,000 monthly machine lease ends if Northgate buys, and the business would redeploy a supervisor on $4,000 per month.

Relevant cost of making, per unit$
Direct materials18.00
Direct labor12.00
Variable overhead6.00
Opportunity cost: 3 hours x $5 contribution lost15.00
Avoidable fixed cost: $3,000 / 2,000 units1.50
Relevant cost of making per unit52.50
Buy price per unit40.00
Saving from buying, per unit12.50

Exclude the absorbed fixed overhead of $9, because the total fixed overhead does not change. Leave the supervisor salary out, because the business pays it either way. The relevant make cost is $52.50 per unit, against a buy price of $40, so buying saves $12.50 per unit, or $25,000 monthly. Therefore, the decision is to buy, provided the supplier is reliable. That point matters for the discussion marks: an answer that ignores quality and delivery risk loses marks even with perfect numbers.

ACCA PM relevant costing worked example 2: a one-off special order

Delta Co received a one-off order for 500 units at $95 each, a total revenue of $47,500. The order needs 1,000 kg of Material A, 400 kg of Material B and 800 labor hours. Material A is in stock: 600 kg bought at $8 per kg, used regularly, replacement cost $10 per kg. Material B sits in stock with no other use and a resale value of $6 per kg. Staff work at full capacity, earn $20 per hour, and moving them loses $14 contribution per labor hour, after deducting labor cost. The order also needs a new supervisor at $2,500, and variable overhead is $3 per unit.

Relevant cost of the special order$
Material A: 1,000 kg x $10 replacement cost10,000
Material B: 400 kg x $6 resale value2,400
Labor: 800 hours x $20 wages16,000
Contribution lost: 800 hours x $1411,200
Variable overhead: 500 units x $31,500
Extra supervisor hired for the order2,500
Total relevant cost43,600
Revenue: 500 units x $9547,500
Incremental profit3,900

The historic cost of Material A, $8 per kg, counts for nothing. Delta already spent $6,000 on design work, so that money never counts, and depreciation of $4,000 is a non-cash item, so exclude both. The incremental profit is $3,900, so Delta accepts the order. However, the margin is thin, so note the risk: the contribution lost could be higher than estimated, and $95 may set a precedent for regular customers.

Shutdown and further processing: two fast decisions

Shutdown decisions use the same rule. First, compare the contribution lost from closing against the fixed costs saved by closing. Therefore, if the fixed costs saved are higher, close. Fixed costs that continue after closure, such as head office rent, remain irrelevant, because the business pays them anyway.

Further processing is a second fast decision. The business already incurred joint costs by the split-off point, so they never enter the calculation. Then compare incremental revenue with incremental cost. If the result is positive, process further. For example, a joint product sells for $30,000 at split-off, or for $48,000 after further processing that costs $12,000. Incremental revenue is $18,000, incremental cost is $12,000, and the gain is $6,000, so the business processes further. The joint costs of $25,000 are irrelevant.

ACCA PM relevant costing exam traps

  • Using historic cost. Historic cost never counts. Instead, use replacement cost for regularly used material, and resale value for material with no other use.
  • Including absorbed fixed overhead. If the total does not change, the overhead is an apportionment, not a cash flow.
  • Forgetting opportunity cost. Freed capacity has a value, and the contribution lost from the alternative use is part of the make cost.
  • Double counting labor. When staff work at full capacity, the relevant cost is wages plus contribution lost, where you measure the contribution after deducting labor cost.
  • Counting depreciation. Depreciation is a non-cash item and never enters a relevant cost calculation.
  • Treating joint costs as relevant. The business incurs joint costs before the split-off point, and they cannot change.
  • Ignoring the discussion marks. Section C awards marks for quality, reliability and staff effects, not just for the number.
  • Using full cost as the minimum price. For a one-off order, the minimum price is the relevant cost.

ACCA PM relevant costing in one page

  • Rule: a cost is relevant only if it is a future, incremental cash flow.
  • Opportunity cost: the benefit given up elsewhere, always relevant when a resource is scarce.
  • Materials: buy at current price, regularly used stock at replacement cost, other stock at resale value.
  • Labor: spare capacity means zero, hiring means extra pay, full capacity means wages plus contribution lost.
  • Overheads: only incremental cash overheads count; absorbed overheads do not.
  • Never relevant: sunk costs, committed costs, depreciation, book values, joint costs, absorbed overhead.
  • Make or buy: compare relevant make cost, including opportunity cost, with the buy price.
  • Special order: accept if revenue exceeds total relevant cost.
  • Shutdown: close only if fixed costs saved exceed contribution lost.
  • Further processing: process further only if incremental revenue exceeds incremental cost.

ACCA PM relevant costing is a short topic with a high mark yield, appearing in Section A, in Section B cases and as a Section C question. Finally, learn the material and labor rules, practice one make-or-buy question and one special order question, and read the ACCA technical article on relevant costs. Find the rest of the set on the ACCA notes hub, including the PM note on budgeting and variance analysis.